November News
RIDD RESTORATION REPORT by Tony Nicholls - 11th November 2026
We were back at Ridd this week to take an early delivery of materials from our supplier – two dumpy bags of Type 1 aggregate and more cement which we are getting through at a rapid rate.
We used the aggregate to fill the central void between the concrete ‘ramps’ adjacent to the central pier having first laid the final course of stone at the back of the slope. The remainder of the aggregate was spread across the top of the pier to provide a level base for the stone paving. We made a good start on laying the paving stones which will provide an authentic finish to the structure.
We were back at Ridd this week to take an early delivery of materials from our supplier – two dumpy bags of Type 1 aggregate and more cement which we are getting through at a rapid rate.
We used the aggregate to fill the central void between the concrete ‘ramps’ adjacent to the central pier having first laid the final course of stone at the back of the slope. The remainder of the aggregate was spread across the top of the pier to provide a level base for the stone paving. We made a good start on laying the paving stones which will provide an authentic finish to the structure.
Laying the final course of stone
Preparing the paving
Paving the top of the pier
It being the 11th November, the team paused work at 11.00 am to join in the national Act of Remembrance – a reminder that we are only able to carry out our voluntary work thanks to the sacrifice of others.
Working parties are currently being held at 9.30am every Wednesday. Please contact Project Manager, Ian Harrison (tel.07557 478371) for more information.
Working parties are currently being held at 9.30am every Wednesday. Please contact Project Manager, Ian Harrison (tel.07557 478371) for more information.
RIDD RESTORATION REPORT by Tony Nicholls - 4th November 2026
A small team assembled at Ridd this week to continue work on the upper docking bays. Our first task was to remove the shuttering from the left side of the ‘ramp’. We were pleased to see that the concrete had formed well without any obvious flaws. We then turned our attention to building a retaining wall at the back of the ramp and laid the first courses of stone.
A small team assembled at Ridd this week to continue work on the upper docking bays. Our first task was to remove the shuttering from the left side of the ‘ramp’. We were pleased to see that the concrete had formed well without any obvious flaws. We then turned our attention to building a retaining wall at the back of the ramp and laid the first courses of stone.
Laying the first courses
Rear wall under contruction
While we were working on the pier our tree surgeons arrived on site to take down two diseased ash trees overhanging the lower incline. (We have been given permission by Devon County Council to remove these). These trees are not only dangerous, they also obstruct the view of the incline from the Tarka Trail. Watching the contractor climb the larger of the two trees, it is clear that this is definitely a job for a young person with a good head for heights! The process of taking down the trees took an entire day but the result has been dramatic. There is now a clear sight line from the top of the incline to the bottom and to the canal beyond. (The small white rectangle is the information board adjacent to the former stable building). The improved view should give the public a much better understanding of this important part of the canal’s infrastructure.
A view of the incline before felling
The ascent begins
Work in progress
View from top of incline after felling
View from of the incline after felling
Working parties are currently being held at 9.30am every Wednesday. Please contact Project Manager, Ian Harrison (tel.07557 478371) for more information.